Non-standard resource availability in Project
July 27th, 2005
A quick way of forcing Project to handle non-standard resource availability:
Filed under Project Management |Task calendars can be used to good effect if, for example, a specialist person or a piece of equipment is only available on certain dates and times. It is also useful when you need to force Project to schedule a task to start on a specific day of the week, say Fridays.